William Tennent High School Facility Updates

 

William Tennent High School Facility Updates

 

September 13, 2019

Picture - Shoring Pole Decoration

Decor


August 27, 2019 - Letter

Ltr1

Ltr2


August 23, 2019 - Typical support structures to be used at the high school.

Picture 1 - 7:00 a.m. receipt and unloading of screw jacks.

Pic

Picture 2 - Delivering the screw jacks to their intended location.

A

Picture 3 - Installation of first screw jack on first floor.

B

Picture 4 - View upward toward ceiling deck within north-south corridor.

C

Picture 5 - View upward within men's restroom supporting haunch.

D

Picture 6 - Corridor view looking north with placement of screw jacks.

F

 


August 22, 2019 - Typical support structures to be used at the high school.

Picture 1 - Typical support structure to be used to shore up the existing haunches within the high school's main north-south corridor.

Pic 7

Picture 2 - Typical support structure to be used to shore up the existing haunches within the high school's main north-south corridor.

Pic 8


August 21, 2019 - Progression of work on remedation

Picture 1 - Typical tape location for intended shoring.

Pic 7

 Picture 2 - First floor corridor depicting the locations of intended shoring.

Pic 3

 Picture 3 - Second floor corridor A Wing depicting the locations of intended shoring.

Pic 5

 Picture 4 - Second floor corridor A Wing removal of fountain to accomodate intended shoring.

Pic 5

 Picture 5 - Second floor corridor A Wing depicting location of intended shoring.

Pic 6


August 20, 2019 - Progression of work on remedation

Picture 1 - Second floor C wing corridor at stairwell with sheetrock removed to expose haunches.

Pic 1

Picture 2 - First floor men’s restroom where ceiling tiles were removed to expose haunches.

Pic 2

Picture 3 - First floor 12 Grade House Office with ceiling tile removed to expose haunches.

Pic 3

Picture 4 - Library workroom ceiling tiles removed to expose haunches.

Pic 4


August 19, 2019 CSD eAlert

We are pleased to inform you that after closing much of William Tennent High School this weekend; we are mostly open for business as necessary. We fully expect to have our first day with teachers on August 27 and first day for students on September 3.

Currently about twenty percent of William Tennent High School is off limits.  Most of our classrooms and communal office and activity space is accessible.  

Our engineering team has fully reviewed the situation. While the need for remediation may not be imminent, in the abundance of care, we elected to provide reinforcement (now) to eliminate any possible risk, and; we are actively working with the construction team to remediate the potential problem areas.  We are acting with an abundance of caution to ensure the safety of our students, faculty, staff and visitors.

We are expecting remediation to begin on Thursday, August 22 with no interruption to scheduled events for the opening of all schools as originally planned. 


August 19, 2019 WTHS eAlert

William Tennent High School will be open for the following functions on August 20th:

  • Athletics 

  • Marching Band

  • Student parking passes

  • The scheduled National Honor Society meeting

Moving forward, our athletics and marching band programs will operate as previously scheduled.


August 17, 2019 CSD eAlert

Please be advised that late on Friday, August 16, 2019, we discovered some structural issues affecting small portions of the building's educational sections in William Tennent High School.

William Tennent High School is currently closed. We are working with our engineering team to address this issue.

The safety and security of students, staff and faculty remains the number one priority of this Board and this Administration.

We will provide updates to the community as soon as the engineers have completed their evaluation.